Clapham Junction

A redevelopment of land for proposed new student accommodation  within its collapse radius to the viaduct and Clapham station.

An Independent Cat III check of the piled crane base design was required by Network Rail together with supporting information. Increasingly, Network Rail look to see the use and influence of the CPA Good Practise Guide “Requirements for Tower Cranes Alongside Railways Controlled by Network Rail” in documents submitted to them.